Gombe Gets 480MW Transmission Capacity As FG Upgrades Grid
The Federal Government has doubled the upstream electrical energy transmission capability of Gombe State to 480 megawatts following the set up of a brand new transformer on the Gombe Transmission Substation.
The improve, alongside the commissioning of a brand new transmission substation in Billiri, is anticipated to enhance electrical energy provide and supply extra capability for greater than 70,000 households.
The Minister of Power, Joseph Tegbe, disclosed this on Thursday through the inauguration of the initiatives, saying they had been designed to deal with rising electrical energy demand in Gombe and neighbouring communities.
At the Gombe Transmission Substation, Tegbe stated a further 300MVA, 330/132kV transformer had elevated the station’s upstream capability from 300MVA to 600MVA, equal to 480MW.
He added that the substitute of an present 30MVA, 132/33kV transformer with a 100MVA unit had elevated the station’s downstream transformation capability to 220MVA, equal to 176MW.
According to him, the upgrades would tackle suppressed demand attributable to the restricted capability of present infrastructure and accommodate extra electrical energy shoppers.
The minister stated the initiatives mirrored President Bola Tinubu’s dedication to strengthening the nationwide grid and bettering electrical energy provide.
At Billiri, the federal government additionally inaugurated a brand new 2x60MVA, 132/33kV transmission substation with a mixed capability of 120MVA, equal to roughly 96MW.
Funded by the World Bank and executed by Chris Ejik International Limited, the power has six outgoing 33kV feeders and is linked to the present Gombe-Savannah-Yola transmission line.
Tegbe stated the substation would enhance electrical energy entry for communities and help agricultural actions, companies and rising settlements within the space.
He urged residents to guard the services in opposition to vandalism, warning that assaults on electrical energy infrastructure might disrupt financial actions and family livelihoods.
The Managing Director of the Transmission Company of Nigeria, Sule Ahmed Abdulaziz, stated the Billiri substation would strengthen the connection between transmission and distribution networks, ease strain on present infrastructure and provides Jos Electricity Distribution Company larger flexibility in supplying electrical energy.
He urged the distribution firm to extend its offtake of obtainable electrical energy to make sure shoppers profit from the funding.
Abdulaziz stated the Gombe Transmission Substation reinforcement contract was awarded to ISIN Electromechanical Industries Limited in June 2021 and accomplished in June 2026.
Representing Governor Muhammadu Yahaya, the state Commissioner for Energy Resources, Sanusi Ahmad, stated the initiatives would help Gombe’s financial growth.
He stated the state was additionally implementing the Electricity Act 2023 by the Gombe State Electricity Law 2025 and the institution of the Gombe State Electricity Regulatory Commission.
The Mai Tangle, Danladi Sanusi, counseled the funding, saying improved electrical energy provide might stimulate companies, appeal to buyers, create jobs and enhance healthcare and schooling.
He, nonetheless, urged the authorities to make sure correct upkeep and efficient utilisation of the services to ensure lasting advantages.
-
Special Reports3 days agoWe’ll not assist you to take over motor parks – Governor Makinde warns NURTW
-
Special Reports3 days agoNAFDAC destroys over 50000 empty branded alcoholic beverage bottles in Lagos
-
Politics2 days ago2027: ADC alleges plot to trigger violence throughout Tinubu's go to to Kebbi
-
News2 days agoVisa, residency reforms: NIS rallies Navy, Army, Police, Customs, others for partnership